SSC CGL 2019 PYQ — Question 75

SSC CGL - 7th June 2019 - Shift 1 • Quantitative Aptitude • Q75

A contractor planned to finish a work in 12 days and employed a certain number of men. However, 6 of them remained absent from the very first day. The rest could finish the work in 20 days. The number of men originally employed were:

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 15

Concept

Understanding

Application

M1 × D1 = M2 × D2

Suppose ‘x’ men were employed at first which were planned to finish the work in 12 days.

 

 

Since 6 men were absent, work got completed in 20 days:

x × 12 = (x – 6) × 20

8x = 120

x = 15