A contractor decided to complete a work in 80 days and employed 60 men at the beginning and 20 men additionally after 20 days and got the work completed as per schedule. If he had not employed the additional men, how many extra days would he have needed to complete the work (round off to the nearest integer)?
Show answer & explanation
Correct answer: B
Explanation
The correct answer is Option 2 i.e. 20 days.
Given:
Time taken to complete the work = 80 days
Number of men worked for 20 days = 60
Number of men worked after 20 days = 80
Concept Used:
Explanation:
After 20 days, the remaining work is don by 80 men in 65 days.
Now, 60 men will complete this work in 48.75 = 49 days
The extra days needed to complete the work = 80 - (40 + 20) =20days.