SSC MTS 2022 PYQ — Question 68

SSC MTS - 19 July 2022 - Shift 2 • Quantitative Aptitude • Q68

X and Y, working together, can complete a work in 30 days, Y and Z, working together, can complete the same work in 40 days. and Z and X, working together, can complete the same work in 24 days. In how many days can X, Y and Z, working together, complete the work?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 20 days.

Total work (LCM of 30, 40, and 24) = 120 units

Efficiency of X and Y = 120/30 = 4 units/day

Efficiency of Z and Y = 120/40 = 3 units/day

Efficiency of Z and X = 120/24 = 5 units/day

Now, X + Y + Z + Y + Z + X = 12

⇒ 2 × (X + Y + Z) = 12 

⇒ X + Y + Z = 6

Thus, X, Y, and Z do 6 units/day.

Hence, the required time taken = 120/6 = 20 days