The ratio of the efficiencies of A, B and C is 7 : 5 : 4. Working together, they can finish a work in 35 days.if A and B work together for 28 days. The remaining work will be completed (in days) by C alone?

Show answer & explanation

Correct answer: B

Explanation

Correct Answer is option 2 i.e. 56

Understanding

Application

Work efficiency 

Total work = Efficiency × Time

Ratio of efficiencies of A, B and C = 7 : 5 : 4

Suppose the efficiencies are 7x, 5x and 4x


 

Working together, they can complete task in 35 days:

Total work = (7x + 5x + 4x) × 35 = 560x

Work completed by A and B together in 28 days = (7x + 5x) × 28 = 336x

Remaining work = 560x – 336x = 224x

Time in which C will complete remaining work = 224x/4x = 56 days