SSC CPO 2019 PYQ — Question 109

SSC CPO Tier I - 12th March 2019 - Shift 2 • Quantitative Aptitude • Q109

The efficiency of A, B, and C are in the ratio 5 : 6 : 9. Working together, they can complete a work in 18 days. In how many days B can alone complete 25% of the work?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is Option 4 i.e. 15

Ratio of efficiency = A : B : C = 5 : 6 : 9

Total efficiency = 5x + 6x + 9x = 20x per day

So,

Total work = Time × Efficiency = 18 × 20x = 360x

1/4th of work = 360x/4 = 90x

B's efficiency = 6x

So,

B alone can complete 25% of the work in = 90x/6x = 15 days