SSC GD 2023 PYQ — Question 48

SSC GD Constable (English) - 16 Jan 2023 - Shift 4 • Quantitative Aptitude • Q48

Suman and Arun together can finish a piece of work in 96 days, Arun and Rahul in 48 days, and Rahul and Suman in 80 days, then Rahul, Suman, and Arun jointly can finish the same work in approximately how many days?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 46 days.

Suman and Arun together can finish the work = 96 days

Arun and Rahul together can finish the work = 48 days

Rahul and Suman together can finish the work = 80 days

Let's assume the total work = LCM of 96, 48, and 80 = 480

Efficiency = Total work/Total time

So, the efficiency of Suman and Arun = 480/96 = 5

Arun and Rahul = 480/48 = 10

Rahul and Suman = 480/80 = 6

Rahul, Suman, and Arun jointly can finish the same work = 480/(21/2) = 45.7 days = 46 days