SSC CGL 2023 PYQ — Question 22

SSC CGL Tier II - 7 March 2023 - Shift 1 • Quantitative Aptitude • Q22

P, Q, and R can finish a work in 5 days, 10 days, and 15 days, respectively, working alone. P and Q work on the first day, P and R work on the second day, P and Q work on the third day, and son on till the work is completed. In how many days the work will be completed?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 72{7}\over{2}.

Given that

P, Q, and R can finish a work in 5 days, 10 days, and 15 days, respectively, working alone.

Total work = LCM of (5, 10, 15) = 30

The efficiencies of

P = 30/5 = 6

Q = 30/10 = 3

R = 30/15 = 2

Now,  P and Q work on the first day, P and R work on the second day, and P and Q work on the third day.

According to the question

In 3 days total work done is (6 + 3) + (6 + 2) + (6 + 3) = 26 completed

then left (30 - 26) = 4  work in next = 4/8 =1/2 days

Hence, Total work complete in (3 + 1/2) days = 7/2 days