SSC CGL 2023 PYQ — Question 54

SSC CGL - 27 July 2023 - Shift 2 • Quantitative Aptitude • Q54

P, Q and R can complete a piece of work in 9, 12 and 18 days, respectively. Working together, how much work can they complete in one day?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 14\frac{1}{4}.

P can complete the work = 9 days

So P's one-day work = 1/9

Q can complete the work = 12 days

So Q's one-day work = 1/12

R can complete the work = 18 days

So R's one-day work = 1/18

The total work they can complete together in one day = 1/9 + 1/12 + 1/18

⇒ 4/36 + 3/36 + 2/36 = 9/36 = 1/4