SSC CHSL 2021 PYQ — Question 55

SSC CHSL - 16 April 2021 - Shift 1 • Quantitative Aptitude • Q55

P can complete five - eighths of a work in 15 days and Q can complete three - fourths of the same work in 30 days. They worked together for 8 days and then P left. How much time will Q working alone, take to complete the remaining work?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 18 days 16 hours.

Concept Used:

Total work = Time × Efficiency

Explanation:

According to the given question,

P can complete five - eighths of a work in 15 days,

P can complete total work in 24 days

Also, Q can complete three - fourths of the same work in 30 days.

Q can complete total work in 40 days

Let the total work to be done be LCM of (24, 40) = 120 units

Efficiency of P = 12024120 \over 24= 5 units/day

And, efficiency of Q = 12040120 \over 40 = 3 units/day

Total work done by (P + Q) in 8 days = (5 + 3) × 8 = 8 × 8 = 64 units

Remaining work = 120 - 64 = 56 units

Q will complete the remaining work alone in 56356 \over 3= 18 days  232\over 3 hours = 18 days 16 hours

Hence the required answer is 18 days and 16 hours.