P and Q together complete a job in 4 days, and R and S complete the same job in 4 days. If P, Q, R, and S work together, how many days do they need to complete the same job?
Show answer & explanation
Correct answer: D
Explanation
The correct answer is option 4 i.e. 2.
Time required for P and Q = days = 22/5 days
Time required for R and S = days = 44/9 days
Total work = 44 (LCM of 22/5 and 44/9)
Efficiency of P and Q = 44/(22/5) = 10 work/day
Efficiency of R and S = 44/(44/9) = 9 work/day
Total efficiency of P, Q, R, and S = 10 + 9 = 19 work/day
Time required = 44/19 = days
Therefore, P, Q, R, and S work together to complete the job in days.