P and Q together complete a job in 425\frac{2}{5} days, and R and S complete the same job in 489\frac{8}{9} days. If P, Q, R, and S work together, how many days do they need to complete the same job?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 2619\frac{6}{19}.

Time required for P and Q = 4254\frac{2}{5} days = 22/5 days

Time required for R and S = 4894\frac{8}{9} days = 44/9 days

Total work = 44 (LCM of 22/5 and 44/9)

Efficiency of P and Q = 44/(22/5) = 10 work/day

Efficiency of R and S = 44/(44/9) = 9 work/day

Total efficiency of P, Q, R, and S = 10 + 9 = 19 work/day

Time required = 44/19 = 26192\frac{6}{19} days

Therefore, P, Q, R, and S work together to complete the job in  26192\frac{6}{19} days.