SSC CGL 2023 PYQ — Question 56

SSC CGL - 25 July 2023 - Shift 2 • Quantitative Aptitude • Q56

A can finish a work in 60 days. He works at it for 15 days and then B alone finishes the remaining work in 48 days. In how much time can A and B working together finish the work?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e.  96031\frac{960}{31} days.

A's work rate = 1/60 work/day

Work done by A in 15 days = (1/60) × 15 = 1/4

Remaining work = 1 - (1/4) = 3/4

B's work rate = (3/4)/48 = 1/64 work/day

Combined work rate of A and B = 1/60 + 1/64 = 31/960 work/day

Time required for A and B = 1/(31/960) = 960/31 days

Therefore, A and B working together can finish the work in 960/31 days.