Eighteen men can complete a work in 14 days. Three women do as much as two men. Five men and six women started the work and continued for 4 days. Subsequently 3 more men joined the group. In how many total days was the work completed ?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 22

We have given,

3 W  = 2 M

W/M = 2/3

The ratio of the efficiency man and woman = 3 : 2

Eighteen men can complete a work in 14 days

Total work = 18 × 14 × 3 = 756

Five men and six women started the work and continued for 4 days.

So, 4 days work = (5M + 6W)  × 4

= (5 × 3 +  6 × 2) × 4

= 108

Remaining work = 756 - 108 = 648

3 more man added in the team

So, remaining work done by (8M + 6W) = (8 × 3 +  6 × 2 = 36)

= 648/36

= 22 days