SSC CHSL 2022 PYQ — Question 55

SSC CHSL - 24 May 2022 - Shift 3 • Quantitative Aptitude • Q55

Avi and Bindu can complete a project in 4 and 12 hours, respectively. Avi begins the project at 5 a.m., and they work alternately for one hour each. When will the project be completed?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 11 a.m. 

Avi can complete a project in 4 hours

Bindu can complete a project in 12 hours

Total work = L.C.M of (4, 12) = 12 units

Efficiency of Avi = 12/4 = 3 units

Efficiency of Bindu = 12/12 = 1 unit

Amount of work done in 2 hours = (3 + 1) = 4 units

12 units of work will be done in = 6 hours

The project will be completed = 5 a.m. + 6 hours = 11 a.m