SSC Selection Post 2025 PYQ — Question 41

SSC Selection Post - Matriculation Level - 25th July 2025 - Shift 1 • Quantitative Aptitude • Q41

A does a work in 10 days and B does the same work in 15 days. How much part of the work is completed in 2 days if they work together?

Show answer & explanation

Correct answer: C

Explanation

A's 1-day work efficiency = 1/10

B's 1-day work efficiency = 1/15

Combined 1-day work efficiency of both = 1/10 + 1/15

= (3 + 2)/30

= 5/30

= 1/6

Therefore, work done in 2 days = 2 × 1/6= 1/3