SSC Selection Post 2025 PYQ — Question 42

SSC Selection Post - Matriculation Level - 25th July 2025 - Shift 1 • Quantitative Aptitude • Q42

A can do a task in 18 days, and B in 9 days. After working together for 4 days, A leaves. How many more days will B take to complete the remaining work?

Show answer & explanation

Correct answer: D

Explanation

A's 1-day work efficiency = 1/18

B's 1-day work efficiency = 1/9

Combined 1-day work efficiency of both = 1/18 + 1/9

= 1/18 + 2/18

= 3/18

= 1/6

Work done in 4 days = 4 × 1/6

= 2/3

Remaining work = 1 - 2/3

= 1/3

Now, B alone will complete the remaining 1/3 of the work.

B's 1-day work efficiency = 1/9

Therefore, time required = (1/3) ÷ (1/9)

= (1/3) × 9

= 3 days