SSC Selection Post 2025 PYQ — Question 39

SSC Selection Post - Higher Secondary Level - 26th July 2025 - Shift 2 • Quantitative Aptitude • Q39

A contractor undertakes to do a piece of work in 60 days with 48 workers. After 30 days, only half the work is done. How many more workers are needed to complete the work in the scheduled time?

Show answer & explanation

Correct answer: C

Explanation

48 × 60 = 48 × 30 + (48 + x) × 30

2880 = 1440 + (48 + x) × 30

1440 = (48 + x) × 30

48 = 48 + x

x = 48 - 48 = 0

Number of additional workers required = 0