SSC Selection Post 2025 PYQ — Question 40

SSC Selection Post - Higher Secondary Level - 26th July 2025 - Shift 2 • Quantitative Aptitude • Q40

A contractor agrees to complete a building in 120 days. He employs 75 workers. After 80 days, only half of the work is completed. To avoid a penalty and finish the remaining work on time, how many additional workers must he employ?

Show answer & explanation

Correct answer: B

Explanation

75 × 80 = W × 40

W = (75 × 80)/40 = 150

Additional workers = 150 − 75 = 75