A company starts constructing buildings for a college. The constructions have 4 stages.

1. buildings proposals

2. proposals approval

3. constructions implemented

4. buildings completed

The above 3D-bar graph indicates the status of constructions for 4 years 2015 to 2018.

The X-axis scale 0, 2,4,6,8,10 indicates 0, 20%, 40%, 60%, 80%, 100%.

Study the bar graph carefully and answer the following question.

Find the total percentage of buildings completed during the total period, 2015 to 2018.

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 50%.

Total period = 2015 to 2018

Stages of construction = 4

Stage 4 (Buildings completed) percentages for each year:

2015: 20%

2016: 10%

2017: 10%

2018: 10%

Total percentage of buildings completed = Sum of percentages for each year

⇒ Total percentage of buildings completed = 20% + 10% + 10% + 10%

⇒ Total percentage of buildings completed = 50%

∴ The total percentage of buildings completed during the period 2015 to 2018 is 50%.