SSC GD 2021 PYQ — Question 75

SSC GD Constable (English) - 18th November 2021 Shift 2 • Quantitative Aptitude • Q75

A can complete 2/3rd of work in 10 days and B can complete 4/5th work in 8 days. They work together for 5 days. The remaining work is completed by C alone in 6 days. In how many days C alone can complete 75% of the same work?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 27

A can complete 2/3rd of work in 10 days

So, A completed a work = 10 × 3/2 = 15 days

B can complete 4/5th work in 8 days.

So, B completed the work = 8 × 5/4 = 10 days

Total work = LCM of 15 and 10 = 30 unit

Efficiency of A = 30/15 = 2 unit/day

Efficiency of B = 30/10 = 3 unit/ day

A and B's 5 days work = (2 + 3) × 5 = 25

Remaining work done by C in 6 days.

So, the efficiency of C = (30 - 25)/C = 6

Efficiency of C = 5/6

ATQ, Total days if C alone finish the 75% of the work = 30×7510056\dfrac{30\times\frac{75}{100}}{\frac{5}{6}} = 27 days