SSC MTS 2026 PYQ — Question 17

SSC MTS - 20 Feb 2026 - Shift 1 • Quantitative Aptitude • Q17

A, B and C together can complete a work in 20 days. A and B together can complete the same work in 25 days. C alone can complete (4/9) of the same work in how many days?

Show answer & explanation

Correct answer: B

Explanation

Given:

A + B + C ⇒ 20 days

A + B ⇒ 25 days

According to the formula:

Work Rate = 1 / Time

Rate of (A + B + C) = 1/20

Rate of (A + B) = 1/25

Rate of C = 1/20 − 1/25

= (5 − 4)/100

= 1/100

Therefore, C alone will complete the entire work in 100 days.

Time required for (4/9) of the work = (4/9) × 100 = 400/9 days