24 men can complete a work in 90 days. 36 men will complete 50 percent of the same work in how many days?

Show answer & explanation

Correct answer: B

Explanation

Given:

24 Men ⇒ Complete the work in 90 days

According to the formula:

Work = Men × Days

Total Work = 24 × 90 = 2160

50% of the Work = 2160 / 2 = 1080

For 36 Men:

Days = 1080 / 36 = 30 days