SSC CGL 2020 PYQ — Question 51

SSC CGL - 3rd March 2020 Shift 1 • Quantitative Aptitude • Q51

A, B and C can individually complete a piece of work in 24 days, 15 days, and 12 days, respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is:

Show answer & explanation

Correct answer: A

Explanation

The correct answer is Option 1 i.e. 

Understanding Application
Tricks
  time work efficiency
A 24   5
B 15 120 8
C 12   10

 

Now

B and C for 3 days

total work done by both = 3(10 + 8)

= 54 unit

Remaining work = 120 - 54

66 unit

Hence

A takes 66/5

=