A and B separately can build a wall in 12 and 16 days, respectively. If they work for 1 day alternatively. Starting with A, in how many days will the wall be built?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e  days.

Understanding/Application

Let the total work to be done be x.

Number of days in which A build the wall = 12 days

Work done by A in 1 day = x/12

Number of days in which B build the wall = 16 days

Work done by B in 1 day = x/16

Work done in 2 days by A and B working alternatively = x/12 + x/16 = 7x/48

Work done by A and B in 12 days working alternatively for 1 day = (7x/48) × (12/2) = 7x/8

Remaining work after 12 days = x - 7x/8 = x/8

Remaining work after A worked for 13th day = x/8 - x/12 = x/24

The remaining work x/24 will be completed B.

Number of days required by B to complete x/24 = (x/24)/(x/16) = 2/3 days

Number of days required to complete work = 12 + 1 + (2/3) = 13(2/3) days