SSC CGL 2022 PYQ — Question 11

SSC CGL Tier II - Quant - 29 Jan 2022 • Quantitative Aptitude • Q11

A and B can do a work in 2623\frac{2}{3}days. B and C together can complete the same work in 48 days, while A and C together can complete the same work in 30 days. How long (in days) will A alone take to complete 60% of the work?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 24

A + B = 80/3 days.

B + C = 48 days.

A + C = 30 days.

Let the total work = 240 units.

Efficiency of A + B = 9 units/day....(1)

Efficiency of B + C = 5 units/day......(2)

Efficiency of A + C = 8 units/day.....(3)

on adding eq (1, 2, 3) we get,

2(A + B + C) = 22 units.

A + B + C one day efficiency = 11 units.

Efficiency of A = 11 - 5 = 6 units/day.

60% of work = 60/100 × 240 = 144 units.

Time taken by A to complete 144 units of work = 144/6 = 24 days.