A and B can do a piece of work in 18 days. They worked together for 12 days and then B left. A finished the remaining work in 10 days. In how many days can A alone complete the work?

Show answer & explanation

Correct answer: A

Explanation

(A + B)'s 1-day work efficiency = 1/18

Work done in 12 days = 12/18 = 2/3

Remaining work = 1/3

A completed 1/3 of the work in 10 days.

Therefore, A's 1-day work efficiency = 1/30

A alone will complete the work in 30 days.