8 men can complete a work in 12 days. How many men are required to complete the same work in 6 days?
Show answer & explanation
Correct answer: C
Explanation
Total work = 8 × 12 = 96 man-days
Men required to complete the work in 6 days = 96/6= 16
SSC Selection Post - Matriculation Level - 1st August 2025 - Shift 1 • Quantitative Aptitude • Q41
8 men can complete a work in 12 days. How many men are required to complete the same work in 6 days?
Correct answer: C
Explanation
Total work = 8 × 12 = 96 man-days
Men required to complete the work in 6 days = 96/6= 16