SSC Selection Post 2025 PYQ — Question 41

SSC Selection Post - Matriculation Level - 1st August 2025 - Shift 1 • Quantitative Aptitude • Q41

8 men can complete a work in 12 days. How many men are required to complete the same work in 6 days?

Show answer & explanation

Correct answer: C

Explanation

Total work = 8 × 12 = 96 man-days

Men required to complete the work in 6 days = 96/6= 16