A and B can do a piece of work in 9 days and 15 dyas, respectively. If they work together, then the work will be completed in:
Show answer & explanation
Correct answer: C
Explanation
The correct answer is option 3 i.e. days.
A can complete the work in 9 days, so A's work rate is:
A’s work rate = 1/9
B can complete the work in 15 days, so B's work rate is:
B’s work rate = 1/15
When A and B work together = 1/9 + 1/15 = =
Hence, time taken by A and B together = 1 ÷ 8/45 = 45/8 = 5 days