SSC GD 2023 PYQ — Question 43

SSC GD Constable (English) - 13 Jan 2023 - Shift 1 • Quantitative Aptitude • Q43

A and B can complete a piece of work in 18 days and 12 days, respectively. They work on alternate days till the work gets completed. How long (in days) would it take A and B to complete the work, starting with A on the first day?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 14.5 days.

A can finish the work = 18 days

B can finish the work = 12 days

Total work = LCM of 18 and 12 = 72

Efficiency of A = 72/18 = 4

B = 72/12 = 6

2 days work done by A and B = 10

14 days work done by A and B = (4 + 6) × 7 = 70

Time taken by A to complete the remaining work A = (72 - 70)/4 = 0.5 day

Total days = 14 + 0.5 = 14.5 day