A and B can complete a piece of work in 15 days and 10 days respectively. They got a contract to complete the work for Rs.75000. The share of A (in Rs.) in the contracted money will be:

Show answer & explanation

Correct answer: C

Explanation

Correct Answer is option 3 i.e. 30,000

Given:

Time taken by A = 15 days

Time taken by B = 10 days

Earning of A and B = Rs. 75000

Concept Used:

Total Work = Efficiency × Time

Earnings are distributed in the ratio of respective efficiencies.

Explanation:

Let the total work be LCM of (15,10) be 30 units.

Efficiency of A = 30/15 = 2 units/day

Efficiency of B = 30/10 = 3 units/day

Share of A = Earnings of A and BEfficiency of A+Efficiency of B×Efficiency of A{{Earnings\ of\ A\ and\ B} \over {Efficiency\ of\ A + Efficiency\ of\ B}} \times {Efficiency\ of\ A}

⇒ 750002+3×2{{75000} \over {2 + 3}} \times {2} = Rs. 30,000