SSC CHSL 2023 PYQ — Question 55

SSC CHSL - 07 Aug 2023 - Shift 1 • Quantitative Aptitude • Q55

4 men and 8 women complete a job in 10 days, and 5 men and 24 women complete the same work in 4 days. In how many days will 1 men and 1 women complete the same work.

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 622962\frac{2}{9} days.

Let the eficiency of 1 man and 1 woman be x and y respectively.

According to the given question,

(4x + 8y) × 10 = (5x + 24y) × 4

⇒ 40x + 80y = 20x + 96y

⇒ 20x = 16y

⇒ x : y = 4 : 5

Total work = (4 × 4 + 8 × 5) × 10 

⇒ 56 × 10 = 560 units

Time taken by 1 man and 1 woman to complete the work = 560/(4 + 5)

⇒ 560/9 = 622962\frac{2}{9}