SSC CGL 2023 PYQ — Question 57

SSC CGL - 25 July 2023 - Shift 1 • Quantitative Aptitude • Q57

4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 25 women complete it?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 16.

Let the efficiency of 1 man and 1 woman be M and W respectively.

According to the given question,

(4M + 6W) × 8 = (3M + 7W) × 10

⇒16M + 24W = 15M + 35W

⇒ 1M = 11W

Total work = (4(11) + 6) × 8

⇒ 50 × 8 = 400

Now, time taken by 25 women = 400/25

⇒ 16 days