SSC CPO 2019 PYQ — Question 116

SSC CPO Tier I - 13th December 2019 - Shift 1 • Quantitative Aptitude • Q116

3 men and 5 women together can complete a work in 6 days, whereas 4 men and 9 women together can do it in 4 days. How many women are required to do the same work in 7 days?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is Option 2 i.e. 12

Let 1 man's 1-day work = x

and 1 woman's 1-day work = y

3 men and 5 women together can complete a work in 6 days:

⇒ 6 × (3x + 5y) = 1

⇒18x + 30y = 1

whereas 4 men and 9 women together can do it in 4 days:

⇒ 4 × (4x + 9y) = 1

⇒ 16x + 36y = 1

On solving the above two equations: y = 1/84

Hence, 1/84 of work done by 1 woman.

Let P be the number of women required to complete the work in 7 days.

⇒ P = 84/7 = 12