24 men can complete a work in 15 days. How many men are needed to complete the same work in 10 days?
Show answer & explanation
Correct answer: C
Explanation
The correct answer is option 3 i.e. 36.
Given that
24 men can complete a work in 15 days
Concept used
M1 D1 = M2 D2
According to the question
24 × 15 = M2 × 10
M2 = 36 men