SSC GD 2024 PYQ — Question 60

SSC GD Const (English) - 21 Feb 2024 Shift 4 • Quantitative Aptitude • Q60

Z1, Z2, and Z3 can do work in 100, 50 and 75 days respectively. All three of them began the work together but Z2 left 15 days before the completion of the work. In how many days was the work completed?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 30 days.

Z1, Z2, and Z3 can do work in 100, 50, and 75 days respectively

L.C.M(100, 50, and 75) = 300

The efficiency of Z1 = 300/100 = 3 units

The efficiency of Z2 = 300/50 = 6 units

The efficiency of Z3 = 300/75 = 4 units

Let the total number of days be n

⇒ (3 + 6 + 4)n + 6(n - 15) = 300

⇒ 13n + 6n - 90 = 300

⇒ 19n = 390

⇒ n = 30

So, the total days to complete the work is 30 days