SSC CGL 2022 PYQ — Question 63

SSC CGL - 11 April 2022 - Shift 2 • Quantitative Aptitude • Q63

X, Y and Z can do a piece of work in 46 days, 92 days and 23 days, respectively. X started the work. Y joined him after 2 days. If Z joined them after 8 days from the beginning, them for how many days did X worked?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 18

X, Y, and Z can do a piece of work in 46 days, 92 days, and 23 days respectively.

Work finished by X in 1 day = 1/46 

Work finished by Y in 1 day = 1/92

Work finished by Z in 1 day = 1/23

Work finished by X and Y in 1 day = 1/46= (1/46) + (1/92) = 3/92

Work X, Y, and Z can finish together in 1 day = (1/46) + (1/92) + (1/23) = 7/92

Work X can do in 2 days = 2/46 = 1/23 

Work X and Y can do in 6 days = 6(3/92) = 9/46 [Z joined them after 8 days from the beginning]

The remaining work = 1 - [(1/23) + (9/46)] = 1 - (11/46) = 35/46 

Time is taken by X, Y, and Z to finish the work = (35/46)/(7/92) = (35/46) × (92/7) = 10 days

Total time of work of X = 8 + 10 = 18 days