X can complete a task in 15 days, and Y can complete the same task in 20 days. If X and Y work on alternate days, starting with X, in how many days will the work be completed?
Show answer & explanation
Correct answer: B
Explanation
SSC GD Const 2025 (English) - 06 Feb 2025 - Shift 3 • Quantitative Aptitude • Q54
X can complete a task in 15 days, and Y can complete the same task in 20 days. If X and Y work on alternate days, starting with X, in how many days will the work be completed?