X and Y together can finish a piece of work in 15 days, while Y alone can finish it in 40 days. X alone can finish the work in:

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e 24 days

Understanding

Application

1/(Days taken by X alone) + 1/(Days taken by Y alone) = 1/(Days taken by X & Y together)

 

1/X + 1/Y = 1/(X+Y)

1/X + 1/40 = 1/15

1/X = 1/15 - 1/40

1/X = (8-3)/120

1/X = 5/120

1/X = 1/24

X= 24 days