X alone can complete a work in 20 days and Y alone can complete the same work in 50 days. They start the work together but after 5 days X leaves the work. How much time will Y take to finish the remaining work?
Show answer & explanation
Correct answer: C
Explanation
The correct answer is option 3 i.e. 32.5 days.
X can complete the work in 20 days, so X's rate of work is:
⇒ 1/ 20 of the work per day
Y can complete the work in 50 days, so Y's rate of work is:
⇒ 1 /50 of the work per day
Together, they complete:
⇒ of the work per day.
In 5 days, they will complete:
⇒ 5 × (7) / (100) = (35) / ( 100) = (7) / (20) of the work.
Remaining work after 5 days:
⇒ 1 - ( 7) / (20) = (13) / (20) of the work.
Time for Y to finish the remaining work:
⇒ days