SSC GD 2019 PYQ — Question 57

SSC GD Constable (English) - 18 Feb 2019 Shift 3 • Quantitative Aptitude • Q57

Working together, A, B and C can complete a work in 36 days. If the efficiency of A, B and C are in the ratio 5: 6: 9, then B alone will complete the same work in:

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 120 days.

Efficiency of A, B and C are in the ratio = 5 : 6 : 9.

Work completed by A, B and C = 36 days

Time taken by A to complete the work = x/5

Time taken by B to complete the work = x/6

Time taken by C to complete the work C = x/9

ATQ -

(1/x/5) + (1/x/5) + (1/x/5) = 1/36

(5/x) + (6/x) + (9/x) = 1/36

20/x = 1/36

x = 20 × 36 = 720

Time Taken by B alone to complete the work = 720/6 = 120 days