SSC GD 2023 PYQ — Question 56

SSC GD Constable (English) - 17 Jan 2023 - Shift 3 • Quantitative Aptitude • Q56

Umesh and Ramesh can complete a work in 28 and 21 days, respectively. Starting with Umesh, they work on alternate days. In how many days will the work be completed?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is Option 4 i.e 24 days.

Umesh can complete a work = 28 days

Ramesh can complete a work = 21 days

Total work = LCM of 28 and 21 = 84 unit

Efficiency of Umesh = 84/28 = 3 unit per day and Ramesh = 84/21 = 4 unit per days

They work alternatively,

So, their 2 days work =  3 + 4 = 7 unit

2 days = 7 unit

2 days × 12 = 7 × 12 unit 

24 days = 84 unit

So, the work will be completed in 24 days.