SSC CHSL 2024 PYQ — Question 69

SSC CHSL - 04 July 2024 - Shift 3 • Quantitative Aptitude • Q69

To finish a work in 12 days, 8 workers are engaged. After 2 days, due to some urgency, the work is to be finished in the next 2 days. How many more workers are to be engaged now to finish it on time?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is Option 2 i.e. 32.

To finish a work in 12 days, 8 workers are engaged

Total work = 8 × 12 = 96 units

In the first 2 days, 8 workers will work

Work done = 8 × 2 = 16 units

Remaining Work = 96 - 16 = 80 units

Let the total number of workers required be x

⇒ x × 2 = 80

⇒ x = 80/2

⇒ x = 40

Additional Workers = 40 - 8 = 32

So, 32 more workers are needed to finish the work on time