SSC CGL 2019 PYQ — Question 81

SSC CGL Tier II Quant - 12/09/2019 • Quantitative Aptitude • Q81

To do a certain work, the ratio of the efficiencies of X and Y is 5 : 4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in ?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 ie 14 days.

5 : 4    [9 × 10 = 90]

5 × 4 = 20 units 

Remaining work = 90 - 20

                          = 70 units 

= 70/5 = 14 days