SSC CGL 2019 PYQ — Question 65

SSC CGL - 10th June 2019 - Shift 1 • Quantitative Aptitude • Q65

The ratio of the efficiencies of A, B and C, to do a certain work is 7 : 3 : 5. Working together, they can complete the work in 21 days. A and C worked together for 15 days. The remaining work will be completed by B alone in?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 45 days

Understanding

Application

Given

Ratio of efficiencies of A, B and C = 7 : 3 : 5

Suppose the efficiencies are 7x, 3x and 5x respectively.

Since together they can complete the work in 21 days:

Hence,

Total work = (7x + 3x + 5x) × 21

= 15x × 21

= 315x

A and C worked together for 15 days:

Work done = (7x + 5x) × 15

= 12x × 15 = 180x

Hence, remaining work = 315x – 180x = 135x

Since B does the remaining work alone:

Time taken by B = 135x/3x = 45 day