SSC CGL 2019 PYQ — Question 66

SSC CGL - 7th June 2019 - Shift 3 • Quantitative Aptitude • Q66

The ratio of the efficiencies of A, B, and C is 3 : 5 : 1. Working together, they can complete a piece of work in 5 days. A and B work together work for 3 days. The remaining work will be completed by C alone in how many days?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is Option 4 i.e. 21 days

Let the efficiencies of A, B, & C be respectively 3, 5 & 1 units

Work done by 3 of them together of day 1 = 3 + 5 + 1 = 9 units

⇒ Total work = 9 × 5

⇒ 45 units

The amount of work completed when A and B work for 3 days = 3(3 + 5)

⇒ 3 × 8 = 24 units

Remaining work = 45 - 24 = 21 units

The number of days taken by C = 21/1

⇒ 21 days