SSC Selection Post 2025 PYQ — Question 97

SSC Selection Post - Matriculation Level - 24th July 2025 - Shift 1 • Reasoning • Q97

The project deadline is non-flexible, yet the current progress shows that the project will not be completed on time. The engineer must decide how to address the time crunch.
Which of the following decision should be taken by the engineer?

Show answer & explanation

Correct answer: C

Explanation

Correct Answer: Re-evaluate and prioritize critical tasks

This question tests an engineer's problem-solving and decision-making abilities.

The question clearly states that 'deadlines are not flexible' (i.e., deadlines cannot be extended). Therefore, the option 'Request an extension' is already ruled out.

'Increasing overtime' or 'Implementing prefabrication techniques' may be temporary solutions, but implementing them without planning can overwhelm the budget or compromise quality.

The most logical and professional approach is to re-evaluate and prioritize critical tasks first. This allows the engineer to identify which tasks are most critical to the project so that the main work can be completed without interruption within the limited timeframe.