SSC Selection Post 2025 PYQ — Question 98

SSC Selection Post - Matriculation Level - 25th July 2025 - Shift 1 • Reasoning • Q98

The pressure to meet the construction deadline is immense. Some project supervisors suggest skipping certain safety tests to speed up the process. What should be the correct decision to take?

Show answer & explanation

Correct answer: C

Explanation

Correct Answer: Schedule parallel safety and construction work

This question tests an engineer or project manager's professional ethics and problem-solving abilities.

Skipping or postponing safety tests (Options 1 and 4): This can be extremely dangerous in any construction project. Compromising safety can lead to major accidents and loss of life and property in the future. Therefore, these options are completely incorrect.

Performing only mandatory tests (Option 2): This is a precautionary approach, but it does not address the problem of deadline pressure.

Schedule parallel safety and construction work (Option 3): This is the most practical and professional approach. It uses fast-tracking techniques, where construction work and safety checks are carefully planned simultaneously (in parallel) to save time without compromising safety standards. This saves time and ensures project safety.