SSC GD 2025 PYQ — Question 45

SSC GD Const 2025 (English) - 07 Feb 2025 - Shift 3 • Quantitative Aptitude • Q45

The number of days to finish a work by A is double the number of days to finish the work by B. The number of days to finish the work by C is half the number of days to finish the work by B. A can finish the work in 12 days. If B works on the 1st day, A works on the 2nd day and C works on the 3rd day, again B works on the 4th day and so on, then the work is finished in _____ days.

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 5.5 .

A = 12 days → 1/12

B = 6 days → 1/6

C = 3 days → 1/3

Every 3 days work = 1/6 + 1/12 + 1/3 = 7/12

After 3 days: 7/12 done

Remaining: 5/12

Next:

Day 4 (B): +1/6 → 9/12

Day 5 (A): +1/12 → 10/12

Day 6 (C): needs 2/12 → Time = (2/12) ÷ (1/3) = ½ day

Total = 5.5 days