The engineering team faces a tight deadline with a fixed budget. The project schedule would benefit from additional resources, but no extra funds are available.
What should the team do?
Show answer & explanation
Correct answer: D
Explanation
The correct answer is: Prioritize budget allocation only for critical tasks.
Why are the other options incorrect?
Hiring temporary workers or renting expensive equipment will add new expenses, which will disrupt the budget.
Negotiating with suppliers is good, but it doesn't guarantee that internal work shortages will be met.