SSC CGL 2019 PYQ — Question 51

SSC CGL - 12th June 2019 - Shift 3 • Quantitative Aptitude • Q51

The efficiencies of A, B and C are in the ratio 2 : 5 : 3. Working together, they can complete task in 9 days. In how many days will C alone complete 40% of that task?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 12

Concept

Understanding

Application

Work efficiency

Total work = Efficiency × Time

 

Ratio of efficiencies of A, B and C = 2 : 5 : 3

Suppose the efficiencies are 2x, 5x and 3x

 

 

Working together, they can complete task in 9 days:

Total work = (2x + 5x + 3x) × 9 = 10x × 9 = 90x

40% of the total work

= 90 × 0.4 = 36

40% of the total work completed by C in = 36/3 = 12 days