SSC CPO 2024 PYQ — Question 101

SSC CPO - 29 June 2024 Shift 2 • Quantitative Aptitude • Q101

Sapna is double efficient as compared to Rakesh. If they both work together on a project and complete it in 48 days, then the number of days in which Sapna alone can complete the project is:

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 72.

Let the total work to be done be 144 units.

Also, let the efficiency of Rakesh be x units/day.

According to the given question, 

Efficiency of Sapna = 2x units/day

Now, time taken by Sapna and Rakesh together to complete the project = 48 days

Total work = Efficiency × Time 

⇒ 144(2x+x)144 \over (2x + x) = 48

⇒ 3x = 3

⇒ x = 1

So, time taken by sapna to complete the project alone = 1442x144 \over 2x

⇒ 1442144 \over 2 = 72 days

Hence the number of days required by Sapna to complete the project is 72.